FY14 SOW and LIB submitted |
B: 119. Manage Restoration Projects |
|
02/28/2014 |
02/25/2014 |
List of Selected Projects (and contingency projects) to be implemented in 2014 |
C: 114. Select habitat improvement actions and identify possible projects for 2014 |
|
09/30/2013 |
09/30/2013 |
Project databases that are maintained and up to date. |
D: 160. Update Project Database |
|
02/28/2014 |
02/25/2014 |
Disseminated data |
E: 161. Create informal summary reports and maps |
|
02/28/2014 |
02/25/2014 |
5 outreach sessions completed |
F: 99. Conduct field and classroom education at local schools |
|
02/28/2014 |
02/25/2014 |
Technical review and input provided to various policy and planning efforts |
G: 122. Input to various Tribal planning and policy efforts |
|
02/28/2014 |
02/25/2014 |
Completed environmental documentation |
H: 165. Environmental Compliance |
|
02/28/2014 |
02/25/2014 |
Attach Progress Report in Pisces |
I: 132. Submit Progress Report for the prior contract period (March 2012) to (Feb 2013) |
|
01/31/2014 |
02/27/2014 |
Completed 2012 and 2013 RPA Report submitted in Taurus |
J: 98. Submit RPA reports for CY 12 and CY13 |
|
02/28/2014 |
02/27/2014 |
Outmigration estimate and other data from screw traps |
K: 157. Operate rotary screw traps |
|
10/31/2013 |
10/31/2013 |
Complete three pass surveys in Satus and Ahtanum Creeks |
L: 157. Conduct spawner surveys |
|
12/15/2013 |
12/15/2013 |
15 miles of completed snorkel surveys |
M: 157. Conduct snorkel surveys |
|
10/15/2013 |
10/15/2013 |
Complete 1500 meters of surveys |
N: 157. Conduct habitat surveys |
|
10/15/2013 |
10/15/2013 |
Water temperature record |
O: 157. Collect water temperature data |
|
11/30/2013 |
11/30/2013 |
Weekly manual discharge measurements |
P: 157. Collect discharge measurements |
|
02/28/2014 |
02/25/2014 |
Monitor water level in monitoring wells |
Q: 157. Collect data from monitoring wells |
|
02/28/2014 |
02/25/2014 |
Wapato Irrigation Project diversions managed for minimum instream flow. |
R: 186. Manage Operation of Upper and Lower WIP canals on Ahtanum Creek |
|
02/28/2014 |
02/25/2014 |
water diversion managed at Olney lateral to provide minimum streamflow |
S: 186. Assist with operation of Olney Lateral |
|
02/28/2014 |
02/25/2014 |
Functioning fences, wells, stock tanks, and habitat improvements |
T: 186. Maintain livestock wells/stock tanks/livestock fences/improved springs |
|
02/28/2014 |
02/25/2014 |
outmigration estimates and timing information |
U: 162. Analyze smolt outmigration data |
|
08/31/2013 |
08/31/2013 |
Index of spawner abundance and spawning distribution |
V: 162. Analyze spawner survey data |
|
07/31/2013 |
07/31/2013 |
Water temperature record and descriptive statistics |
W: 162. Analyze water temperature data |
|
11/30/2013 |
11/15/2013 |
Habitat metrics and indicators |
X: 162. Analyze habitat survey data |
|
12/31/2013 |
12/01/2013 |
Spatial Fish Density |
Y: 162. Analyze snorkel survey data |
|
12/31/2013 |
11/01/2013 |
technical review recommendations provided |
Z: 122. Project engineering support |
|
02/28/2014 |
09/30/2013 |
Simcoe Creek Bank Stabilization Construction |
AB: 29. CCR30322 CANCELED WE - Simcoe Creek Bank Stabilization Project (construction) |
|
09/30/2013 |
|
Construction oversight |
AC: 100. CCR30322 CANCELED WE - Simcoe Creek Bank Stabilization Project (construction oversight) |
|
09/30/2013 |
|
Technical Review Recommendations provided |
AE: 122. CCR30322 NEW WE - Project consultation on construction and engineering |
|
02/28/2014 |
|
Toppenish Creek Reach Assessment and Restoration Strategy |
AF: 114. CCR30322 NEW WE -Toppenish Creek Reach Assessment and Restoration Strategy |
|
02/28/2014 |
|
South Fork Ahtanum Forest Road Improvement |
AG: 38. CCR30322 NEW WE - South Fork Ahtanum Forest Road Improvement Project |
|
10/31/2013 |
|
Upper Toppenish Creek Culvert Removal and Ford Installation |
AH: 85. CCR30322 NEW WE - Upper Toppenish Creek Culvert Removal and Ford Installation |
|
10/31/2013 |
|